How Long Does It Take to Build a Quality Garden Room?
If you’re considering adding a garden room to your home, one of your first questions is likely: how long will it take to build? The good news is that for most homeowners in the UK, a garden room can be built quickly and efficiently—without needing planning permission—thanks to Permitted Development rules. With a well-prepared site and a clear brief, we can typically complete a fully finished, plastered garden room with electrics in under two weeks. Whether you’re creating a home office, gym, studio, or extra living space, this article explains exactly how long the process takes, what’s involved at each stage, and why modern timber-framed garden rooms can be delivered faster than you might think—without cutting corners on quality.
Built Under Permitted Development = No Delays
The majority of garden rooms we install are designed to fall within Permitted Development, which means no need for full planning permission. As long as the building is:
-
Under 2.5m high (when within 2m of a boundary)
-
Not intended for permanent sleeping accommodation
-
Covers less than 50% of your garden
…then you’re good to go. This alone saves 6–8 weeks of administrative delay and allows us to move from site survey to build in a matter of days—not months.
A Typical Timeline: Just 7–14 Days On-Site
While many imagine a garden room taking months to build, a streamlined construction process using pre-cut timber frames, efficient teams, and coordinated logistics means the entire on-site build usually takes 7–10 working days. In that time, you’ll receive a:
-
Fully insulated and plastered interior
-
Professionally installed electrical system
-
High-quality cladding and roofing
-
Foundation tailored to your ground conditions
Here’s how it all comes together.
Site Survey and Quote (1–3 Days)
Once you enquire, we typically arrange a site survey within a few days. We assess:
-
Access to your garden
-
Ground level and drainage
-
Your preferred layout and use
You’ll then receive a detailed quote based on your specification. There’s no drawn-out design phase—just straightforward, efficient planning based on proven templates with room for customisation.
Groundworks and Foundation (1–2 Days)
Once the start date is set, we begin by preparing the ground. Most garden rooms require one of the following foundations:
-
Concrete slab
-
Timber frame on pads
-
Ground screws
We recommend the best option based on your soil, drainage, and layout. This phase includes levelling the area, clearing debris, and ensuring the base is flat and ready. It typically takes 1 to 2 days.
Structural Build and External Shell (2–4 Days)
Once the base is in, we begin erecting the timber frame, which has been pre-cut and prepared off-site. In this stage we complete:
-
Walls, roof, and floor insulation
-
Waterproofing membranes
-
External cladding (timber or composite)
-
EPDM or other long-life roofing
-
Double-glazed doors and windows
This typically takes 2–4 days, depending on the size and features of the room. By the end, the structure is fully watertight, meaning internal work can proceed regardless of the weather.
First-Fix Electrics and Plasterboarding (1–2 Days)
After the shell is complete, our qualified electricians install:
-
Wiring for sockets, lighting, and heating
-
Network cables (if required)
-
Connection prep for consumer unit
With first-fix wiring in place, we then move on to plasterboarding and jointing the interior walls and ceiling—laying the foundation for a smooth finish. All this is typically completed in 1 to 2 days.
Plastering and Drying (1–2 Days)
A fully plastered interior makes all the difference in creating a true extension of your home. Our plasterers skim all interior surfaces in 1 day. Drying time can vary slightly depending on the season, but with good airflow and low humidity, plaster is usually paint-ready in 48 hours or less.
Second-Fix Electrics and Finishes (1–2 Days)
Once plaster is dry, we return for the final touches, including:
-
Installing sockets, switches, and downlights
-
Connecting to the main fuse board
-
Testing and certifying the system
We’ll also take care of: -
Skirting and trim
-
Painting and decorating (if included)
-
Final clean and customer handover
All of this typically takes 1 to 2 days, wrapping up your project in less than two weeks from the first dig.
Optional Extras That May Extend the Build Slightly
While most builds finish within 10 working days, a few features may extend your schedule slightly:
-
Toilet or shower room (adds 2–3 days for plumbing and tiling)
-
Decking or landscaping (adds 1–2 days depending on size)
-
Custom cabinetry or media installs
These additions are entirely optional, and we’ll discuss timeframes with you upfront if you choose to include them.
Summary Timeline
Here’s a quick overview of the standard 2-week garden room build process:
-
Day 1–2: Groundworks and base installation
-
Day 3–6: Structural build and external finish
-
Day 7: First-fix electrics and plasterboarding
-
Day 8: Plastering
-
Day 9–10: Second-fix electrics, finishes, clean-up
Total Time: 7–10 working days (under 2 weeks in most cases)
Why This Build Speed Doesn’t Compromise Quality
Fast doesn’t mean rushed. We achieve quick build times by using:
-
Experienced installation teams
-
A tried-and-tested timber frame system
-
Off-site prep and pre-cut components
-
Smart scheduling and full project management
You still get a high-quality, durable structure—built to last, fully insulated, and finished to the standard of a modern home interior. All work is signed off and certified to meet UK building standards.
When to Book and How to Prepare
To keep your project on schedule:
-
Book your consultation at least 4–6 weeks ahead
-
Confirm your design choices early
-
Ensure clear access to the build site
-
Let us know about nearby utilities or boundaries
With your preparation in place, we’ll take care of the rest—from groundworks to handover.
Conclusion: A High-Quality Garden Room in Under 2 Weeks
If you're looking to add usable space to your home quickly and cost-effectively, a garden room built under Permitted Development offers the perfect solution. With the right team and a smart construction process, you can go from a bare patch of garden to a fully finished, insulated, electrified, and plastered room in as little as 7–10 working days. No lengthy delays, no red tape, and no compromises on comfort or build quality. Whether you're working from home, starting a new hobby, or simply craving more space, your garden room can be ready in a fraction of the time you'd expect—without sacrificing the things that matter.